Bathroom remodel before, during, after

Before:

- Before - as it was built

During:

- Day 01 / Tuesday / 04OCT16 - Kevin puts Nick and Gato on the demolition
- Day 02 / Wednesday / 05OCT16 - Kevin & tile setter discuss the plan
- Day 03 / Wednesday / 12OCT16 - Kevin sets drain, etc 2B ready for hot mop
- Day 04 / Friday / 14OCT16 - hot mop
- Day 05 / Monday / 17OCT16 - Oleg on bathroom tile installation
- Day 06 / Tuesday / 18OCT16 - Oleg on bathroom tile installation
- Day 07 / Wednesday / 19OCT16 - Oleg on bathroom tile installation
- Day 08 / Thursday / 20OCT16 - Oleg on bathroom tile installation
- Day 09 / Friday / 21OCT16 - Oleg on bathroom tile installation
- Day 10 / Monday / 24OCT16 - bathroom tile installation continues...
- Day 10 / Monday / 24OCT16 - Richard paints bathroom/bedroom/office
- Day 11 / Tuesday / 25OCT16 - bathroom tile installation continues... NOT...
- Day 11 / Tuesday / 25OCT16 - Richard paints bathroom/bedroom/office
- Day 12 / Wednesday / 26OCT16 - bathroom tile installation on hold...
- Day 12 / Wednesday / 26OCT16 - Capital Frooring install bedroom/office floor tile
- Day 13 / Thursday / 27OCT16 - Capital Frooring install bedroom/office floor tile
- Day 14 / Friday / 28OCT16 - Capital Frooring install bedroom/office floor tile
- Day 15 / Saturday / 29OCT16 - Capital Frooring install bedroom/office floor tile
- Day 16 / Monday / 31OCT16 - Kevin installs new toilet
- Day 16 / Monday / 31OCT16 - Richard paints base boards
- Day 17 / Tuesday / 01NOV16 - move STUFF back into bedroom/office
- Day 17 / Tuesday / 01NOV16 - Kevin installs new toilet
- ... and...
- Day ?? / Someday / ...... Oleg resume bathroom tile installation
- Day ?? / Someday / ...... Constatine on plumbing & hardware installation
- Day ?? / Someday / ...... Richard finish painting bathroom
- ... time passes... tic tic tic...
- Day 18 / Friday / 18NOV16 - Oleg on bathroom tile installation

... photograph by Russell Holder
... and finaly... 4 missing tiles have arrived...

0730hrs, ready for Oleg... most everything moved during the 3 week wait...
... and a lot of examination of WHERE everything was moving to...
... to the bedroom, to the office, to Oregon, to Goodwill, ...
photograph by Russell Holder
... photograph by Russell Holder

photograph by Russell Holder
... photograph by Russell Holder
photograph by Russell Holder
... photograph by Russell Holder


... hey... look... in the meantime a room divider from Home Depot has arrived...
photograph by Russell Holder
... photograph by Russell Holder
photograph by Russell Holder
... photograph by Russell Holder

photograph by Russell Holder
... photograph by Russell Holder


... just the right width, just the right height, hung a picture on my side...
photograph by Russell Holder
... photograph by Russell Holder

photograph by Russell Holder
... photograph by Russell Holder


... the shower... collecting dust for the last 3 weeks...
photograph by Russell Holder
... photograph by Russell Holder
photograph by Russell Holder
... photograph by Russell Holder


0830hrs, Oleg arrives to install the last four mis-ordered/
mis-shipped/re-ordered (re-ordered HOT!!) double bull-nose 6" tiles...
OOPS!!!... while moving stuff that was stored in the shower for
the last month, the bottom of a glass block box came apart, a glass block
hit the deck and a corner broke off... Oleg continues...
...
...approaching noon Oleg heads out to Sierra Glass BLock to get another glass block...
arrives there at 1210hrs to finda sign on the door: "Closing today at noon"
- proof that Uncle Murphy is alive and well...
...
... [sigh]... to be continued Monday...

photograph by Russell Holder
... photograph by Russell Holder


... well, only lack top row of glass blocks and grout...
... notice baseboard tiles are there now...
photograph by Russell Holder
... photograph by Russell Holder
photograph by Russell Holder
... photograph by Russell Holder

- Day 19 / Monday    / 21NOV16 - Oleg on bathroom tile installation
- Day 20 / Tuesday   / 22NOV16 - Constatine on plumbing & hardware installation
- Day 20 / Tuesday   / 22NOV16 - Richard finish painting bathroom
After:

- After - TA DAAAAAAA!!!