Bathroom remodel before, during, after

Before:

- Before - as it was built

During:

- Day 01 / Tuesday / 04OCT16 - Kevin puts Nick and Gato on the demolition
- Day 02 / Wednesday / 05OCT16 - Kevin & tile setter discuss the plan
- Day 03 / Wednesday / 12OCT16 - Kevin sets drain, etc 2B ready for hot mop
- Day 04 / Friday / 14OCT16 - hot mop
- Day 05 / Monday / 17OCT16 - bathroom tile installation
- Day 06 / Tuesday / 18OCT16 - bathroom tile installation
- Day 07 / Wednesday / 19OCT16 - bathroom tile installation
- Day 08 / Thursday / 20OCT16 - bathroom tile installation
- Day 09 / Friday / 21OCT16 - bathroom tile installation
- Day 10 / Monday / 24OCT16 - bathroom tile installation continues...
- Day 10 / Monday / 24OCT16 - Richard paints bathroom/bedroom/office

... photograph by Russell Holder
Same paint for the remodel as in family room and kitchen...
IMG_3780.jpg
... photograph by Russell Holder


1330hrs, Richard, a very proficient, efficient painter,
is well underway...
IMG_3769.jpg
... photograph by Russell Holder
IMG_3770.jpg
... photograph by Russell Holder


IMG_3771.jpg
... photograph by Russell Holder
IMG_37722jpg
... photograph by Russell Holder


1415hrs, Oleg has finished the pony wall face, the window top row and
began the pan mudding and layout...
IMG_3773.jpg
... photograph by Russell Holder
IMG_3774.jpg
... photograph by Russell Holder


IMG_3775.jpg
... photograph by Russell Holder
IMG_3776.jpg
... photograph by Russell Holder


1430hrs, pan mudding... four 5gal buckets worth
IMG_3777.jpg
... photograph by Russell Holder


1600hrs, floor tile installation...
IMG_3778.jpg
... photograph by Russell Holder


1730hrs, done for the day.. floor completed and hump laid out...
IMG_3779.jpg
... photograph by Russell Holder
hmmmmmm... bathroom tile installation is taking longer than estimated...

- Day 11 / Tuesday   / 25OCT16 - bathroom tile installation continues...
- Day 11 / Tuesday   / 25OCT16 - Richard paints bathroom/bedroom/office
- Day 12 / Wednesday / 26OCT16 - bedroom/office flooring tile installation
- Day 13 / Thursday  / 27OCT16 - bedroom/office flooring tile installation
- Day 14 / Friday    / 28OCT16 - bedroom/office flooring tile installation
- Day 15 / Saturday  / 29OCT16 - bedroom/office flooring tile installation
- Day 16 / Monday    / 31OCT16 - Kevin installs new toilet
- Day 16 / Monday    / 31OCT16 - Richard paint base boards
- Day 17 / Tuesday   / 01NOV16 - move STUFF back into bedroom/office
- ... and...

After:

- After - TA DAAAAAAA!!!