- Day 01 / Tuesday / 04OCT16 - Kevin puts Nick and Gato on the demolition
- Day 02 / Wednesday / 05OCT16 - Kevin & tile setter discuss the plan
- Day 03 / Wednesday / 12OCT16 - Kevin sets drain, etc 2B ready for hot mop
- Day 04 / Friday / 14OCT16 - hot mop
- Day 05 / Monday / 17OCT16 - bathroom tile installation
- Day 06 / Tuesday / 18OCT16 - bathroom tile installation
0800hrs, Olig arrives and removes panels covering shower valve
0830hrs, Kevin arrives and levels the shower hot/cold knobs w/copper plumbing tape & brass screws
1200hrs, Olig's work on nitches and 2 coats of red guard...
- Day 07 / Wednesday / 19OCT16 - bathroom tile installation - Day 08 / Thursday / 20OCT16 - bathroom tile installation - Day 09 / Monday / 24OCT16 - Richard paints bathroom/bedroom/office - Day 10 / Tuesday / 25OCT16 - Richard paints bathroom/bedroom/office - Day 11 / Wednesday / 26OCT16 - Capital Frooring install - Day 12 / Thursday / 27OCT16 - Capital Frooring install - Day 13 / Friday / 28OCT16 - Capital Frooring install - Day 14 / Saturday / 29OCT16 - Capital Frooring install - Day 15 / Monday / 31OCT16 - Kevin installs new toilet - Day 15 / Monday / 31OCT16 - Richard paint base boards - Day 16 / Tuesday / 01NOV16 - moveSTUFF back into bedroom/office - ..., during,... After: - After - TA DAAAAAAA!!! Back: back to Bathroom Remodel KF!