Before:
During:
- Day 01 / Tuesday / 04OCT16 - Kevin puts Nick and Gato on the demolition
- Day 02 / Wednesday / 05OCT16 - Kevin & tile setter discuss the plan
- Day 03 / Wednesday / 12OCT16 - Kevin sets drain, etc 2B ready for hot mop
- Day 04 / Friday / 14OCT16 - hot mop
- Day 05 / Monday / 17OCT16 - bathroom tile installation
- Day 06 / Tuesday / 18OCT16 - bathroom tile installation
- Day 07 / Wednesday / 19OCT16 - bathroom tile installation
- Day 08 / Thursday / 20OCT16 - bathroom tile installation
- Day 09 / Friday / 21OCT16 - bathroom tile installation
- Day 10 / Monday / 24OCT16 - bathroom tile installation continues...
- Day 10 / Monday / 24OCT16 - Richard paints bathroom/bedroom/office
- Day 11 / Tuesday / 25OCT16 - bathroom tile installation continues... NOT...
- Day 11 / Tuesday / 25OCT16 - Richard paints bathroom/bedroom/office
- Day 12 / Wednesday / 26OCT16 - bathroom tile installation on hold...
- Day 12 / Wednesday / 26OCT16 - bedroom/office flooring tile installation
- Day 13 / Thursday / 27OCT16 - bedroom/office flooring tile installation
- Day 14 / Friday / 28OCT16 - bedroom/office flooring tile installation - Day 15 / Saturday / 29OCT16 - bedroom/office flooring tile installation - Day 16 / Monday / 31OCT16 - Kevin installs new toilet - Day 16 / Monday / 31OCT16 - Richard paint base boards - Day 17 / Tuesday / 01NOV16 - move STUFF back into bedroom/office - ... and... - Day ?? / Someday / ??OCT16 - resume bathroom tile installation - Day ?? / Someday / ??OCT16 - Richard finish painting bathroom After: - After - TA DAAAAAAA!!! Back: back to Bathroom Remodel KF!