Before:
During: - Day 1 - Kevin puts Nick and Gato on the demolition - Day 2 - Kevin & tile setter discuss the plan - Day 3 / Thursday / 13OCT16 - Kevin sets drain, etc 2B ready for hot mop - Day 5 / Monday / 17OCT16 - bathroom tile installation - Day 6 / Tuesday / 18OCT16 - bathroom tile installation - Day 7 / Wednesday / 19OCT16 - bathroom tile installation - Day 8 / Thursday / 20OCT16 - bathroom tile installation - Day 9 / Monday / 24OCT16 - Richard paints - Day 10 / Tuesday / 25OCT16 - Richard paints - Day 11 / Wednesday / 26OCT16 - Capital Frooring install - Day 12 / Thursday / 27OCT16 - Capital Frooring install - Day 13 / Monday / 31OCT16 - Richard touch up - Day 14 / Tuesday / 01NOV16 - Kevin installs new toilet - ..., during,... After: - After - TA DAAAAAAA!!! Back: back to Bathroom Remodel KF!