Bathroom remodel before, during, after
Before:
- Before - as it was built
During:
- Day 01 / Tuesday / 04OCT16 - Kevin puts Nick and Gato on the demolition
- Day 02 / Wednesday / 05OCT16 - Kevin & tile setter discuss the plan
- Day 03 / Wednesday / 12OCT16 - Kevin sets drain, etc 2B ready for hot mop
- Day 04 / Friday / 14OCT16 - hot mop
- Day 05 / Monday / 17OCT16 - Oleg on bathroom tile installation
- Day 06 / Tuesday / 18OCT16 - Oleg on bathroom tile installation
- Day 07 / Wednesday / 19OCT16 - Oleg on bathroom tile installation
- Day 08 / Thursday / 20OCT16 - Oleg on bathroom tile installation
- Day 09 / Friday / 21OCT16 - Oleg on bathroom tile installation
- Day 10 / Monday / 24OCT16 - bathroom tile installation continues...
- Day 10 / Monday / 24OCT16 - Richard paints bathroom/bedroom/office
- Day 11 / Tuesday / 25OCT16 - bathroom tile installation continues... NOT...
- Day 11 / Tuesday / 25OCT16 - Richard paints bathroom/bedroom/office
- Day 12 / Wednesday / 26OCT16 - bathroom tile installation on hold...
- Day 12 / Wednesday / 26OCT16 - Capital Frooring install bedroom/office floor tile
- Day 13 / Thursday / 27OCT16 - Capital Frooring install bedroom/office floor tile
- Day 14 / Friday / 28OCT16 - Capital Frooring install bedroom/office floor tile
- Day 15 / Saturday / 29OCT16 - Capital Frooring install bedroom/office floor tile
... photograph by Russell Holder
... and here we are... bathroom shower tile work still on hold...
flooring completed Friday, yesterday, so, no floor installation necessary today...
0800hrs, now that it is daylight... notice a BUNCH of problems...
- previous workers, e.g., the demo crew, the hot mop dude and
the tile setter, put down drop cloths all the way from the
front door to their work area; the flooring installers did
NOT use any drop cloths, and, now there is thinset or grout
from the bedroom door, all the way down the hall, through the
family room, across the new vinyl flooring in the living room
and in the entry...
- the hall...
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
- the family room...
... photograph by Russell Holder
... photograph by Russell Holder
- the living room...
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
- the entry...
... photograph by Russell Holder
... photograph by Russell Holder
and now that it is daylight... notice a BUNCH of transgressions
against Monday/Tuesday's paint job...
- the installers were told paint was applied to the walls on Monday/
Tuesday before they started work on Wednesday
- recall the tile cutting saw setup on Thursday's photos with
visqueen taped to the walls...
- - that did not seem to hurt the 2 day old paint job
- TV cable taped to the wall to be out of the way...
- - that did not seem to hurt the 2 day old paint job
... photograph by Russell Holder
HOWEVER...
- there are a variety of places where the paint job will have to be corrected:
- - splatter on the paint on the toilet room LHS entrance...
... photograph by Russell Holder
- - chip in the paint on the toilet room RHS entrance & splatter below...
... photograph by Russell Holder
... photograph by Russell Holder
- - ... & splatter on the front edge...
... photograph by Russell Holder
- - something yukko on the window sill in the toilet room
... photograph by Russell Holder
- - splatter on LHS of Sharon's closet entrance & more splatter below...
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
- - splatter on Sharon's LHS closet door & more splatter below...
... photograph by Russell Holder
... photograph by Russell Holder
- - splatter on RHS of Sharon's closet wall...
... photograph by Russell Holder
- - splatter on RHS of Sharon's closet entrance...
... photograph by Russell Holder
- - splatter on the walls around the room...
- - - walking walls east, south, west, east
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
- - ... around to my closet now... & chip in RHS face...
... photograph by Russell Holder
... photograph by Russell Holder
- - ... continuing... splatter on the walls around the room...
... photograph by Russell Holder
... photograph by Russell Holder
Well... we'll see what the painter has to say on Moonday...
- today and tomorrow, Saturday and Sunday: continue to move
some stuff back that wont be in the way on Monday...
- - Saturday, Capital Flooring was interested in out feed back, viz.,
floor looks outstanding, but, wish installers had
used drop cloths and not chipped the paint in places.
- - Capital Flooring recommended a wet rag to correct most thinset
and/or grout splatter on walls and throughout house...
that worked!
- - Spartan accomodations this weekend, but, can lay flat on matress...
... photograph by Russell Holder
... photograph by Russell Holder
- - Sunday, went to California Automobile Museum (442-6802) to see
the "Live Free: California Motorcycle Culture" exhibit
- would you like to know more?... click here
- Monday, toilet gets installed and baseboards get painted and
paint transgressions corrected...
... bathroom shower tile work will still be on hold...
- Day 16 / Monday / 31OCT16 - Kevin installs new toilet
- Day 16 / Monday / 31OCT16 - Richard paints base boards
- Day 17 / Tuesday / 01NOV16 - move STUFF back into bedroom/office
- Day 17 / Tuesday / 01NOV16 - Kevin installs new toilet
- ... and...
- Day ?? / Someday / ??OCT16 - resume bathroom tile installation
- Day ?? / Someday / ??OCT16 - Richard finish painting bathroom
After:
- After - TA DAAAAAAA!!!
Back:
back to Bathroom Remodel
KF!