Bathroom remodel before, during, after
Before:
- Before - as it was built
During:
- Day 01 / Tuesday / 04OCT16 - Kevin puts Nick and Gato on the demolition
- Day 02 / Wednesday / 05OCT16 - Kevin & tile setter discuss the plan
- Day 03 / Wednesday / 12OCT16 - Kevin sets drain, etc 2B ready for hot mop
- Day 04 / Friday / 14OCT16 - hot mop
- Day 05 / Monday / 17OCT16 - bathroom tile installation
- Day 06 / Tuesday / 18OCT16 - bathroom tile installation
- Day 07 / Wednesday / 19OCT16 - bathroom tile installation
- Day 08 / Thursday / 20OCT16 - bathroom tile installation
- Day 09 / Friday / 21OCT16 - bathroom tile installation
- Day 10 / Monday / 24OCT16 - bathroom tile installation continues...
- Day 10 / Monday / 24OCT16 - Richard paints bathroom/bedroom/office
- Day 11 / Tuesday / 25OCT16 - bathroom tile installation continues... NOT...
- Day 11 / Tuesday / 25OCT16 - Richard paints bathroom/bedroom/office
- Day 12 / Wednesday / 26OCT16 - bathroom tile installation on hold...
- Day 12 / Wednesday / 26OCT16 - bedroom/office flooring tile installation
... photograph by Russell Holder
0530hrs, up early today to finish emptying bedroom/office area before flooring dudes arrive...
- eta between 8:30 & 9:30am...
... and so here we are... bathroom shower tile work on hold...
0915hrs, bedroom/office is about as empty as it's going to get...
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
1000hrs, evvvvvery thing else is out of the bedroom/office and into the familyroom/kitchen
- our poor cramped puppies...
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
1200hrs, another pass on emptying the garage...
- stuff destined for Goodwill
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
1230hrs, all purple carpet is gone...
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
1500hrs, "woor" tile floor is happening...
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... hmmmmmmm... not all that big, but... how deep???
- (no evidence in hall or family room)
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... and outside... looks like about 1/64th inch crack...
... photograph by Russell Holder
... photograph by Russell Holder
... photograph by Russell Holder
... and more towards the front of the house another crack perhaps 1/32nd inch...
... photograph by Russell Holder
1830hrs, that's it for today...
... photograph by Russell Holder
- Day 13 / Thursday / 27OCT16 - bedroom/office flooring tile installation
- Day 14 / Friday / 28OCT16 - bedroom/office flooring tile installation
- Day 15 / Saturday / 29OCT16 - bedroom/office flooring tile installation
- Day 16 / Monday / 31OCT16 - Kevin installs new toilet
- Day 16 / Monday / 31OCT16 - Richard paint base boards
- Day 17 / Tuesday / 01NOV16 - move STUFF back into bedroom/office
- ... and...
- Day ?? / Someday / ??OCT16 - resume bathroom tile installation
- Day ?? / Someday / ??OCT16 - Richard finish painting bathroom
After:
- After - TA DAAAAAAA!!!