Bathroom remodel before, during, after

Before:

- Before - as it was built

During:

- Day 01 / Tuesday / 04OCT16 - Kevin puts Nick and Gato on the demolition
- Day 02 / Wednesday / 05OCT16 - Kevin & tile setter discuss the plan
- Day 03 / Wednesday / 12OCT16 - Kevin sets drain, etc 2B ready for hot mop
- Day 04 / Friday / 14OCT16 - hot mop
- Day 05 / Monday / 17OCT16 - bathroom tile installation

1200hrs, Kevin arrives and levels the shower hot/cold knobs
1230hrs, Olig arrives
- gets location of mural, slide bar, grab bars, & nitches
1300hrs, Kevin goes to pick up wall tile
- the 6"x6" double bullnose is only single
- Capital Flooring says supplier's error, will re-order... HOT...
- notice the very faint sparkles in this tile... cooooool...

... photograph by Russell Holder
IMG_3694.jpg
... photograph by Russell Holder
IMG_3693.jpg
... photograph by Russell Holder

IMG_3693.jpg
... photograph by Russell Holder


1300hrs, Olig installs blocks for hardware, then waterboard, then applies tape
1700hrs, Olig done for the day... will resume tomorrow at 0800 hrs
IMG_3685.jpg
... photograph by Russell Holder
IMG_3686.jpg
... photograph by Russell Holder

IMG_3687.jpg
... photograph by Russell Holder
IMG_3688.jpg
... photograph by Russell Holder


1715hrs, hmmmmm... shower hot/cold knobs not level again...
- Kevin says will install a 2x4 to make them STAY level
IMG_3690.jpg
... photograph by Russell Holder
IMG_3691.jpg
... photograph by Russell Holder

IMG_3692.jpg
... photograph by Russell Holder

- that's about 1/16" drop at HOT knob on LHS...
- not a lot, but definately noticible, and... bugs me
IMG_3692.jpg
... photograph by Russell Holder
- Day 06 / Tuesday   / 18OCT16 - bathroom tile installation
- Day 07 / Wednesday / 19OCT16 - bathroom tile installation
- Day 08 / Thursday  / 20OCT16 - bathroom tile installation
- Day 09 / Monday    / 24OCT16 - Richard paints bathroom/bedroom/office
- Day 10 / Tuesday   / 25OCT16 - Richard paints bathroom/bedroom/office
- Day 11 / Wednesday / 26OCT16 - Capital Frooring install
- Day 12 / Thursday  / 27OCT16 - Capital Frooring install
- Day 13 / Friday    / 28OCT16 - Capital Frooring install
- Day 14 / Saturday  / 29OCT16 - Capital Frooring install
- Day 15 / Monday    / 31OCT16 - Kevin installs new toilet
- Day 15 / Monday    / 31OCT16 - Richard paint base boards
- Day 16 / Tuesday   / 01NOV16 - move STUFF back into bedroom/office
- ..., during,...

After:

- After - TA DAAAAAAA!!!

Back:

back to Bathroom Remodel

KF!